Development and Refurbishment Finance for Conversion Companies
Converting a building with staged finance? See how a contract change or lower sale value affects the money you need to finish.
Discuss a staged conversion facilityWhat the facility commits, line by line
A development or heavier refurbishment lender usually agrees a total facility, then splits it into lines with their own release rules. The agreement sets when the special purpose vehicle (SPV) can use each part of the facility. This page follows one illustrative SPV converting a vacant three-storey office building in England into eight flats for sale. Permission is in place, the building contract is a £1,200,000 fixed price and the contractor is ready to start.
| Facility line and when it is released | Amount |
|---|---|
| Site advance At purchase completion, towards the £780,000 price | £500,000 |
| Works tranche In stages against work the monitor certifies, once the SPV has paid for the first £180,000 of works | £1,020,000 |
| Contingency line Only for cost increases the lender approves | £60,000 |
| Interest and fee reserve Retained to meet finance charges, not available for works | £150,000 |
| Total facility | £1,730,000 |
The SPV puts in £586,000: £310,000 at purchase to cover the rest of the price and £30,000 of purchase costs, £180,000 of early works and £96,000 of professional fees. The budgeted cost is £2,316,000. The assumed gross development value (GDV), meaning the expected sale value of all eight flats, is £2,800,000. How cash moves before the first draw is covered in the development and conversion companies overview. This page picks up once building is under way.
Month five: does the money left cover the work left?
Work worth £560,000 has been certified. The strip-out then exposes corroded steel beams, and building control asks for extra fire separation between flats. The contractor prices that work at £86,000 and adds six weeks, with £22,000 of extended site costs. The SPV also wants a £32,000 kitchen and flooring upgrade to support sale prices. Before anything is instructed, the monitor's update compares the cost to complete with every source of money still available.
Cost to complete £840,000
- Original contract balance £1,200,000 less £560,000 certified £640,000
- Variations and extended site costs £86,000 + £32,000 + £22,000 £140,000
- Fees and extra interest £42,000 fees, £18,000 interest beyond the reserve £60,000
Money still available £789,000
- Undrawn works tranche Reserved for the original stages £640,000
- Unspent contingency line Needs lender approval for each use £60,000
- SPV cash available £34,000 kept for fees plus a £55,000 buffer £89,000
- Not covered £840,000 less £789,000 £51,000
The undrawn £640,000 is already spoken for. It matches the balance of the original contract, stage by stage. Drawing it for the variation would leave the final stages unfunded. Approving the facility did not approve this change. The lender decides whether, and from which line, any of it is paid.
Which costs the facility may fund once the monitor has checked them
| Cost still to pay | Cost | Facility may fund |
|---|---|---|
| Original contract balance | £640,000 | £640,000 works tranche |
| Structural and fire separation work | £86,000 | £60,000 contingency, if approved |
| Kitchen and flooring upgrade the SPV chose | £32,000 | £0 |
| Contractor's extra six weeks on site | £22,000 | £0 |
| Professional and monitoring fees | £42,000 | £0 |
| Interest beyond the retained reserve | £18,000 | £0 |
| Total | £840,000 | £700,000 |
The SPV must pay
£140,000SPV cash available
£89,000To find before instructing the change
£51,000The structural work is necessary, but the £60,000 contingency line covers only part of it. The remaining £26,000, the chosen upgrade, the extra site costs, the fees and the extra interest fall to the SPV. The example assumes the monitor supports the change and the lender approves £60,000 from the contingency line.
Forecast: what the variation and a lower valuation do to the exit
Here is the same building under three outcomes at month five. In the third, the valuer's update puts each flat at £330,000 rather than £350,000, giving a GDV of £2,640,000. The agreement in this example limits the facility to 65% of GDV.
| Cost to complete | £674,000 |
|---|---|
| Facility funds, after checks | £640,000 |
| SPV pays | £34,000 |
| SPV cash left over | £55,000 |
| Contingency unused | £60,000 |
| Facility to GDV | 61.8% |
| Forecast profit after allowing for the full contingency | £428,000 |
| Cost to complete | £840,000 |
|---|---|
| Facility funds, after checks | £700,000 |
| SPV pays | £140,000 |
| SPV cash shortfall | £51,000 |
| Contingency unused | £0 |
| Facility to GDV | 61.8% |
| Profit before tax | £322,000 |
| Cost to complete | £840,000 |
|---|---|
| Facility funds, after checks | £686,000 |
| SPV pays | £154,000 |
| SPV cash shortfall | £65,000 |
| Contingency unused | £0 |
| Facility to GDV | 65.0% |
| Profit before tax | £165,200 |
At £2,640,000, a 65% limit allows £1,716,000, which is £14,000 below the £1,730,000 facility. In this illustration the lender restores the limit by cancelling £14,000 of the undrawn works tranche, so the SPV pays that much more towards the remaining stages. The agreement sets the lender’s options, which could include asking for a cash payment or agreeing a waiver. The pre-tax forecast falls from £428,000 after allowing for contingency to £165,200, or 6.3% of the lower GDV, which leaves little room for a slow sale or a further price cut.
Before the contractor starts the extra work
- Put the variation to the monitor and lender first. Ask in writing whether the contingency line can fund the structural and fire work, and whether six more weeks breach any programme date in the agreement.
- Separate necessary work from choices. The £32,000 upgrade is optional. Defer or drop it unless agents' evidence shows it protects the sale prices.
- Fix the price of the change. Have the contractor and your quantity surveyor agree the variation and extension of time under the building contract, so the cost to complete is a figure rather than an estimate.
- Evidence the extra cash. Show where the £51,000, or £65,000 if values fall, will come from and when it will reach the SPV's account, ahead of the next draw request.
- Recheck the exit. Update sales evidence and the expected selling period. If the SPV may keep and let the flats instead, a refinance lender will make its own valuation and rental assessment.
Light refurbishment or heavier conversion: which conditions apply?
Describe the scope, permissions and contract. Providers use those details to decide whether they can consider the work and how they would release funds.
Light refurbishment
- Typical works
- Non-structural improvement of a building that stays in the same use, such as kitchens, bathrooms, decoration or rewiring.
- How works money is provided
- It varies by provider. Some release it at completion or in one or two tranches. Others expect the borrower to pay and rely on the improved value.
- What the lender checks
- Schedule of works and budget, property condition, any permissions the works need, and whether the lender permits the works at all.
- If the scope grows
- Structural items found during the works can take the case outside the lender's light-works terms. Tell the lender before going further.
Heavier refurbishment or conversion
- Typical works
- Structural alteration, change of use, extra units or reconfiguration, usually under a building contract with a professional team.
- How works money is provided
- Staged draws against certified progress, often with a lender-appointed monitor reporting on progress and cost to complete.
- What the lender checks
- Planning or prior approval, building regulations, the contractor, contract, programme, cost plan, contingency, source of equity, GDV and exit.
- If the scope grows
- The monitor reports the variation and the lender retests whether the remaining funds are enough. Extra funding or revised terms need its agreement.
If structural work is possible, plan for the heavier conditions from the start. A conversion that begins on light-works terms and then turns structural may need a new facility partway through, with fresh valuation, legal and arrangement costs. Ask a surveyor to assess the structure before you choose the route.
If the purchase must complete before the contract and permissions are ready, see bridging finance for development and conversion companies, which tests the bridge's repayment. The general property development finance, property refurbishment finance and commercial bridging finance guides cover structures, costs and security. For other ownership models, return to commercial property and asset ownership.
Questions about staged development and refurbishment finance
Does an approved development facility pay for a contract variation?
Not automatically. Undrawn works money is normally allocated to stages already priced, and a variation needs the lender's agreement before it can be drawn. In the example the £640,000 left in the works tranche matches the original contract balance, so the variation must come from the contingency line, if approved, or the SPV's own cash. Ask how the lender treats variations before you instruct the contractor.
What is cost to complete, and who checks it?
It is an estimate of everything still needed to finish the scheme, including variations, fees and extra interest, not just the contract balance. A lender-appointed monitor or quantity surveyor typically updates it with each report and compares it with the undrawn facility and the SPV's available cash. Give the monitor priced variations and the revised programme so the figure stays current.
Can unspent contingency cover a cost increase?
Only if the agreement allows it and the lender approves that cost. Some lenders limit contingency to unforeseen work the monitor accepts, and an upgrade you choose may not qualify. In the example the £60,000 line covers part of the £86,000 structural and fire work, leaving £26,000 for the SPV. Confirm the contingency rules in writing before you sign.
What happens if the valuer lowers the completed value during the build?
The lender may retest its value-based limits and ask the SPV to bring the loan back within them. That could mean more equity, a smaller undrawn facility or a waiver, depending on the agreement. In the example a £160,000 fall in GDV puts the £1,730,000 facility £14,000 over an assumed 65% limit. Check which tests are repeated during the build and when.
Is light refurbishment finance enough for a conversion?
Usually not where works are structural, add units or change the use. Lenders define light and heavy works differently, so describe the real scope. Structural problems found during strip-out can take a light-works case outside its terms. If that is possible, ask whether a staged facility with monitoring would fit better from the start.
What should we send the lender before instructing a variation?
Send the contractor's priced variation, the reason for it, the revised programme and your quantity surveyor's view. Add an updated cost to complete, the source of any extra SPV cash and fresh sales evidence if values have moved. Ask for written confirmation of what will be funded, and from which facility line, before the work starts.
Bring the contract, the draw schedule and any change
Tell us which company owns the building, the planning position, the contractor and building contract, what has been certified so far, any priced variation, how much cash the SPV can add and the latest view of sale values. NBS Finance acts as a commercial finance broker and introducer. Providers assess the scheme, borrower and team, and set any offer, fees, security and guarantees. Property used as security may be repossessed if repayments are not made.