Finance for Pump and Dewatering Hire Companies
Compare extra hire you can bill with the cost of replacing a pump that stays on site.
Discuss your pump hire financeThe site ran four weeks over. What did it earn, and what did it cost you?
Example only. A pump hire firm has a dewatering pump on hire to a groundworks contractor at £650 a week, booked for six weeks. The site runs over. The pump was due back for another customer's job starting in week 8, so the firm hires one in from another supplier. Here is when billing starts and stops under the hire terms assumed in this example.
-
Week 6
Extension agreed by email
BillableWeeks 7 to 10 continue at the agreed rate. Get the new end date, or the notice needed to end it, in writing.
-
Start of week 11
Site says it no longer needs the pump
Billable but likely queriedThe pump has stopped, but nobody has asked for an off-hire number. Under the example terms, hire continues until one is issued.
-
End of week 11
Off-hire number issued
Hire charges stopThe pump is still on site. Your pump is still not available for the next job.
-
Week 12
Collected, cleaned and checked
Only if your terms allowThe first collection fails at a locked gate. The pump comes back contaminated after pumping sewage.
Agreed and billable
- Extension, weeks 7 to 10 4 weeks at £650
- £2,600
Billable only if the contract and the customer agree
- Week 11, before the off-hire number Released on site but still on hire under the terms
- £650
- Engineer call-outs to restart the pump 3 visits at £180, if the contract has a call-out rate
- £540
- Failed collection If your terms charge for attempts the customer prevents
- £250
- Decontamination after sewage If the contract lets you charge for it
- £400
- At risk
- £1,840
Costs the overrun caused elsewhere
- Pump hired in for the week-8 job Weeks 8 to 12, 5 weeks at £520
- £2,600
- Delivery and collection of that pump
- £300
- Cost you carry
- £2,900
Who you hire to changes when you get paid
The same pump on the same site can be paid on very different terms. Work out which of these applies to each job before you rely on the cash.
-
Direct to a utility, site owner or main contractor
- What triggers payment
- Your invoice against their purchase order, on their payment terms.
- What to check
- Whether the order covers the extra weeks. An invoice above the order value may be held until the order is amended.
-
To a groundworks contractor working for someone else
- What triggers payment
- Your terms with the contractor, who may itself be waiting for payment.
- What to check
- In England, Wales and Scotland, the Housing Grants, Construction and Regeneration Act 1996 makes "pay when paid" terms ineffective in construction contracts, except on insolvency. Under section 105, delivering plant to site is not a construction operation unless the same contract also covers installation. A hire-only agreement may fall outside. Take advice on your own contracts.
-
Pumps supplied with installation or an operator
- What triggers payment
- Check whether the contract pays against an invoice, a valuation or a payment notice, and when you can submit it.
- What to check
- For construction work, HMRC distinguishes plant hire with an operator from hire-only. Check the whole contract and the supplier’s status. Where a deduction applies, allow for the cash actually due.
Match the gap to the right kind of finance
-
Customers owe you for agreed hire
Invoice finance may advance part of agreed, undisputed hire invoices from business customers. Disputed weeks, unagreed call-outs and cleaning charges are often excluded until accepted. Bring off-hire numbers and extension emails.
-
Overruns keep forcing you to hire in
Equipment finance may spread the cost of another pump. Compare its monthly payment with what you actually spent on cross-hire over the last year, including delivery. A new pump does not shorten an overrun.
-
You have value in pumps or generators
Asset refinance may release cash from owned kit, after paying off any finance still owing. Kit stuck on a site that runs over still has to be found, identified and valued.
-
You need to cover a defined gap
A business loan or working capital facility may cover a gap like the £2,900 in the example if you can show when the overrun invoices will be paid.
For a wider plant fleet, see plant hire finance. If you dig and dewater your own sites, groundworks and civils finance covers measured work, retentions and CIS. The repair, rental and circular supply chains guide compares keeping a spare ready with hiring one in, and refrigeration service and hire covers standby cooling. If your assets move through reusable packaging contracts, see finance for pallet and crate pooling.
Questions about finance for pump and dewatering hire
When do hire charges stop if the site no longer needs the pump?
It depends on your hire terms. Some terms keep charges running until an off-hire or collection number is issued, or until the equipment is returned and receipted. In the example, the pump stopped at the start of week 11 but the off-hire number came at the end of it, so £650 may be due under those assumed terms, subject to agreement and verification. Ask customers to request an off-hire number as soon as they release the pump.
Can we charge for standby when the pump is on site but not running?
Usually only if the contract says so. Standard hire continues while the pump is on hire, whether or not it is running, if your terms provide for that. Separate standby, attendance or call-out rates need to be agreed in the contract or order. Treat anything not agreed as at risk, as the example does.
Our customer is a groundworks contractor waiting to be paid. Can it make us wait too?
That depends on your contract. In a construction contract, the Housing Grants, Construction and Regeneration Act 1996 makes payment conditional on the payer being paid by someone else ineffective, except on insolvency. But delivering plant to site is not a construction operation under the Act unless the contract also covers installation. Check which applies to your hire and take advice if a payment is being held back.
Does CIS apply to pump hire?
HMRC treats plant supplied with an operator for construction differently from hire-only. For mixed contracts, check the scope of the work with your contractor or adviser before estimating deductions. The amount you receive may differ from the invoice total.
Can invoice finance cover overrun hire invoices?
It may cover agreed hire owed by business customers, once invoiced. In the example, the £2,600 of confirmed extension hire is the strongest part. The £1,840 of queried items may be excluded until the customer accepts them. Keep extension emails, off-hire numbers and collection records with each invoice.
Should we buy another pump instead of hiring one in?
Compare the monthly payment on another pump with what you have actually paid for cross-hire over the last year, including delivery and collection. If overruns are rare, hiring in may cost less. If they happen on most jobs, owning a spare may help, but the payment continues when it sits in the yard.
What should we bring to an enquiry?
Bring your fleet list with serial numbers and ownership, an aged debtor list, and hire agreements or orders for your largest customers. Add extension and off-hire records for recent overruns, your cross-hire spend and any CIS statements. Say which gap you want to close.
Show us where the overrun leaves you short
Tell us who you hire to, how they pay, how often sites run over and what you spend hiring in. We can discuss which routes might fit, including when you are unsure. NBS Finance is a commercial finance broker and introducer, not a lender. Providers assess the business and decide eligibility, terms and charges. An enquiry does not guarantee an offer.
Tell us about your pump hire business