Development and Refurbishment Finance for Repositioning Projects
Refurbishing a building in phases while tenants keep trading? See what the lender’s surveyor certifies, which costs may be left out and how the money to finish is checked.
Discuss a staged refurbishmentPhase the works around the tenants who stay
With a staged refurbishment facility, the lender agrees a works budget and releases money in instalments as work is completed and checked. When part of the building stays let, the phasing also decides which tenants are affected, and when.
Illustration only. A property company owns a freehold parade of six shops in England. Units 1 to 3 are let and trading, paying £60,000 a year between them. Units 4 to 6 are empty and rated EPC F, so they need upgrading before they can be relet. The facility repays the existing £400,000 loan and provides a £360,000 works line, which is 80% of a £450,000 budget. That budget is £420,000 of works and a £30,000 contingency.
-
Phase 1 · months 1–3
Roof, gutters and rear service yard
£120,000
- Unit 1 Trading
- Unit 2 Trading
- Unit 3 Trading
- Unit 4 Works
- Unit 5 Works
- Unit 6 Works
Scaffold at the rear only. Keep rear doors, bin stores and deliveries usable, and agree noisy hours with each tenant.
-
Phase 2 · months 4–8
Empty units 4 to 6: services, energy upgrades and shopfronts
£210,000
- Unit 1 Trading
- Unit 2 Trading
- Unit 3 Next door
- Unit 4 Works
- Unit 5 Works
- Unit 6 Works
Keep shared services to the let units running. Check party walls and dust control next to Unit 3. Market Units 4 to 6 during the works.
-
Phase 3 · months 9–10
New frontages for the let units
£90,000
- Unit 1 Hoarding
- Unit 2 Hoarding
- Unit 3 Hoarding
- Unit 4 Ready to let
- Unit 5 Ready to let
- Unit 6 Ready to let
Work outside trading hours where possible, and keep each shop entrance open and signed. Agree in writing any rent concession for lost window display.
- Trading, little disruption
- Trading, works nearby
- Works on the unit or its frontage
Before you fix the phases, check what each lease allows: access for works, notice, working hours and whether costs can be recharged through the service charge. Show the lender how rent from Units 1 to 3 continues through each phase.
What the surveyor certifies and what the lender releases
At the end of month 6, the contractor’s interim valuation for Phase 2 comes to £150,000. The company pays the contractor. The lender’s monitoring surveyor checks the claim against the approved schedule of works and certifies what is eligible. The lender then releases 80% of that figure.
| Contractor’s claim for the period | £150,000 |
|---|---|
| Fit-out for a new Unit 4 tenant Not on the approved schedule | −£18,000 |
| Shopfront frames stored off site Delivered but not fixed | −£12,000 |
| First-fix work valued lower The surveyor considers it unfinished | −£6,000 |
| Certified as eligible | £114,000 |
| Released by the lender, 80% | £91,200 |
| Paid by the company this period £150,000 claim less £91,200 released | £58,800 |
Of the £58,800, £22,800 is the company’s 20% share of the certified work and £18,000 is the fit-out the lender will not fund. The remaining £18,000 covers the frames and the unfinished work. Once those are certified at the next draw, 80% of them, £14,400, comes back.
Before you submit a draw: will this item be released?
Released once certified
- Fixed work on the approved schedule
- Contingency items the lender has approved in writing
- Work signed off where the lender requires it
Waits for a later draw
- Materials delivered but not fixed, or stored off site
- Work the surveyor considers unfinished
- Items waiting for a certificate or test result
Company pays
- Its share of each certified amount
- Tenant fit-out or incentives not on the schedule
- Professional and monitoring fees, in this example
Is there still enough money to finish?
Before each release, the lender or its surveyor typically checks the amount still needed to finish against the undrawn facility and the money the company has committed. Here is that check after Draw 2, run to the end of Phase 3 in month 10, with rent from the let units paying the interest.
| Works still to certify, including the £30,000 contingency | £216,000 |
|---|---|
| Professional fees still due | £14,000 |
| Monitoring visits still due | £3,000 |
| Interest at an assumed 0.75% a month | £18,768 |
| Total | £251,768 |
| Undrawn works line | £172,800 |
|---|---|
| Company’s 20% of the works still to certify | £43,200 |
| Company cash for fees and monitoring | £17,000 |
| Rent from Units 1 to 3, £5,000 a month | £20,000 |
| Total | £253,000 |
Plan as forecast
£1,232 spareUnit 1 given two months rent-free during its frontage works
£2,768 shortThe works side balances: £172,800 undrawn plus the company’s £43,200 equals the £216,000 still to certify. The thin margin is on running costs. The rent covers the interest with only £1,232 to spare. A £4,000 concession to Unit 1 leaves the company to find £2,768. The company has to fund that concession and keep enough cash for the works. A tenant leaving partway through would leave a bigger gap.
Hypothetical figures, not lending criteria or an offer. Interest is serviced monthly on the drawn balance: £587,200 in months 7–8 and £664,000 in months 9–10, after Draw 3 releases £76,800. The contingency is assumed undrawn until after month 10. Rents are £24,000, £21,000 and £15,000 a year. No VAT, business rates on empty units or tax are included.A published example of works with tenants in place
Investec has published a 2026 deal for a Bristol office building: a 48-month facility made up of an initial tranche and a capital expenditure tranche, funding a phased refurbishment while tenants stayed and rental income was retained. This is the lender’s own account of a large transaction. It does not describe NBS involvement or set terms for any other case.
Tenants, leases and the empty units
What the leases allow
Read each lease for access rights, notice, working hours and any promise not to disturb the tenant’s trade. Ask your solicitor before planning works that block a shop entrance or window.
Service charge recovery
Whether roof or yard costs can be recharged depends on the lease wording. Do not count on recovering improvement costs from tenants. The lender will ask how the budget is paid if they are not recovered.
Leases ending during the works
In England and Wales, a tenant with a protected business lease can usually ask for a new lease when it ends. A landlord can oppose only on set grounds, one of which is intending substantial works that cannot reasonably be done without possession. Take legal advice before relying on getting a unit back.
Energy ratings for the empty units
In England and Wales, a new lease of a covered unit rated F or G generally needs at least EPC E or a registered exemption. Price the upgrades into Phase 2 and get the new EPCs before you market the units.
If a scope change hits a bridge partway through the works, see bridging finance for refurbishment and repositioning. For a term loan once the units are let, see commercial mortgages for refurbished buildings. A change of use or conversion is covered by development and refurbishment finance for conversion companies. The refurbishment and repositioning overview compares the routes by how much work is needed. The general property refurbishment finance and property development finance guides cover structures and costs.
Questions about staged refurbishment with tenants in place
Can tenants stay in the building during a staged refurbishment?
Often, if the leases allow the works and the phases are planned around the tenants. Check access rights, notice and working hours in each lease, and keep entrances and shared services usable. Tell the lender which tenants stay in each phase and how their rent continues. Agree any concessions in writing.
What does the lender’s surveyor certify before a release?
Work completed on the approved schedule, valued at the date of the visit. The surveyor compares the contractor’s claim with what is fixed and finished, and may value some items lower or leave them for a later draw. The lender then releases its agreed share of the certified amount, so the release is usually less than the contractor’s claim.
Which costs might a refurbishment facility exclude?
It depends on the facility, but commonly items outside the approved schedule, such as a tenant’s own fit-out, and materials that are not yet fixed. Fees and contingency may also be excluded unless agreed. In the example, the lender leaves out £36,000 of a £150,000 claim. £18,000 of that will never be funded, and £18,000 waits for the next draw. Ask for the eligibility rules before you sign.
What is the cost-to-complete check?
It compares everything still needed to finish with the undrawn facility, the money the company has committed and any income it can rely on. If there is a gap, the lender may hold back the next release until the company adds cash. Update it with every draw, and include interest and fees, not just works.
Can rent from the let units pay the interest during the works?
It can, if the lender agrees to serviced interest and the rent is reliable. In the example, £5,000 a month covers interest of up to £4,980 a month. A rent concession or a tenant leaving would fall on the company. Show the lender the leases, rent received and any breaks or expiries within the works period.
Can we get a let unit back to refurbish it?
Check the lease and take legal advice before relying on vacant possession. In England and Wales, a protected business tenant may have renewal rights. Substantial works can be grounds to oppose renewal if the statutory conditions are met. Phasing the works around the tenant, or agreeing terms with it, is often simpler.
Bring the phasing plan, the tenancy schedule and the budget
Tell us which company owns the building, which units stay let in each phase, the schedule of works and contingency, the contractor and how the facility would be repaid or refinanced. NBS Finance acts as a commercial finance broker and introducer. Providers assess the property, the works and the borrower, and set any offer, fees, security and guarantees. Property used as security may be repossessed if repayments are not made.